7.5 Data-center projects and opposition

Project Backers / size Status / opposition Label
Pecém, Caucaia (CE), TikTok/ByteDance TikTok: more than R$200bn, including R$108bn in equipment to 2035; operating from 2027; 100% renewable, water reuse. g1 reports "R$ 580 bilhões" (an unreconciled discrepancy). 200 MW in a ZPE (export-processing zone). Built by Omnia; wind power deal with Casa dos Ventos (US$2bn). MPF and DPU civil action (MPF release dated 10 Sept 2026) against Omnia and Semace; the state of Ceará and Caucaia were later added as defendants. It seeks to block operation until the Anacé people get free, prior and informed consultation (ILO 169) and a full EIA/Rima is done. Licensing used a simplified report (RAS). The site is about 2 km from the Lagamar do Cauípe APA, which overlaps an Anacé land under Funai study. An MPF-commissioned expert report called the RAS "tecnicamente inadequado e insuficiente". Semace says there are no norms for data centers. The Anacé had sued earlier (2025). [V] TikTok; [V] MPF; [V] g1; [V] Folha; [V] Rest of World; Casa dos Ventos [V-s] (Reuters 401)
Rio AI City (Olympic Park/Barra) Elea (controlled by I Squared Capital since Apr 2026; Piemonte 33%). On 8 Jun 2026 at Web Summit Rio, Mayor Eduardo Cavaliere and Elea CEO Alessandro Lombardi announced Elea's US$550m investment and an MoU with CCPar. 1.5 GW initially, up to 3 GW by 2032. Elea's plan is about US$10bn; R$2.5bn near term. No organised opposition found [U] [V] Prefeitura; [V] Valor Intl
Scala AI City, Eldorado do Sul (RS) Scala (DigitalBridge). It requested 5 GW by 2033 (not authorised). 1,800 MW granted, which the assembly report says is "40% superiores ao consumo médio residencial do RS". Governor Eduardo Leite (PSD) promised simplified licensing in a 2024 protocol of intentions. No public hearings or prior consultation. The CNDH visited in late March 2026 and recommends a national regulatory framework. A state-assembly subcommittee report (26 Mar 2026) flags energy, environmental and political impacts. [V] Brasil de Fato; [V] Matinal; [V] FNDC/CNDH; 2025 origin [V-s] (Intercept Brasil 403); "77,760 m³/day" [U] (not found in the source)
Paracatu (MG), 1 GW Atlas Renewable Energy (owned by a BlackRock arm); R$35bn; partial operation planned for Dec 2027. Atlas has also applied for 1 GW in Janaúba. The council and residents learned of it from reporters. About 80% of the municipality lies in declared water-conflict areas. It could use up to 1.2 million L/day even at the Redata efficiency threshold. Atlas calls it "very preliminary". At least 68 data centers are planned in 37 municipalities. The motive: absorbing curtailed solar output. [V] Mongabay/Intercept Brasil, 10 Sept 2026
Microsoft / AWS / Google, São Paulo Microsoft R$14.7bn (announced 26 Sept 2024). AWS R$10.1bn (US$1.8bn) to 2034. Google Cloud "doubling" capacity by 2030. Little local opposition reported [U] [V] Microsoft; [V] AWS; [V] Bloomberg Línea
Redata, Lei 15.504 (15 Sept 2026) Suspends PIS/Cofins/IPI and import duty on equipment; the suspension becomes a zero rate once conditions are met. Conditions: 100% renewable or low-emission power; WUE ≤ 0.05 L/kWh, measured annually; at least 10% of capacity for the domestic market, with export or own use barred where domestic demand goes unmet; 2% of benefited value into R&D, at least 40% of it in the North, Northeast and Centre-West. A 180-day cure period, after which suspension becomes cancellation. The "5-year" term in the research note was not found in the texts read. No national environmental-licensing rule for data centers (Mongabay; Semace). PL 1.680/2025 is still in the Chamber [V-s]. [V] Planalto; [V] Câmara
Chile, Google Cerrillos (Dataluna, US$200m) The original design drew up to 169 L/s from the Santiago Central aquifer. The Second Environmental Court partly annulled the permit in Feb 2024; Google renounced it in Sept 2024 and redesigned for air cooling. A new pertinence consultation (PERTI-2026-7923, filed 29 Jul 2026, shown "Resuelta" with no response date) asks to confirm that environmental review is not needed. Its outcome is not visible in the record [U]. OLCA and MOSACAT object. [V] BioBio, 4 Sept 2026; [V] SEIA record
Uruguay, Google Canelones Google Four neighbouring families appealed to the Environment Ministry over noise, landscape and lack of consultation. The original water figure ("7.6 million L/day") and the redesign figure are not in this source. [V] El Observador; water figures [R]
Mexico, Querétaro Microsoft, AWS, Google and others Drought and blackouts. Microsoft says its Querétaro sites used 40 million litres in FY2025 (BBC, 28 Aug 2025). Communities ask for water priority and public data. [V] BBC; [V] Guardian 2024; [V] WIRED es; [V] Pulitzer
Argentina, Stargate (OpenAI + Sur Energy) Letter of intent signed 10 Oct 2025 for up to US$25bn / 500 MW. For the Kargieman link see Direction 4. A year on: no construction, no final investment decision, no RIGI filing. Mapuche opposition to Patagonian AI data centers [U] (not found in the sources read). [V] Chequeado; [V-s] Letra P
Paraguay, X8 Cloud USTDA-backed, near Asunción, on Itaipú power. Phase 1 ~US$8bn; target 5 GW. The CEO says the US work "also involves authorization to buy Nvidia GPUs". Also: Hive (US$400m), which cites Paraguay's alignment, and DFC/Taiwan talks for 10 MW. — [V] BNamericas
Colombia, Atlántico hyperscale USTDA grant of US$1,002,285 for technical, financial and environmental feasibility studies. US-made or US-developed equipment; "USTDA assistance is available only to American companies". Barranquilla lands five submarine cables. — [V] USTDA, 29 Sept 2026; [V] Gobernación del Atlántico; [V] BNamericas

Regional oversight.

  • At an IACHR hearing (Aug 2026), groups from Chile, Mexico and the US asked for safeguards, including temporary moratoria. [V] Gaceta Ambiental, 17 Aug 2026
  • The IACHR's rapporteur on economic and social rights (REDESCA) made similar recommendations in Feb 2026. [V-s] (OAS 403)